REMOVAL FORMS:
Sides of foundation, columns, beams and walls | 2 days |
Under sides of slab up to 4.5m span | 7 days |
Under sides of slabs above 4.5m span and Under sides of beam and arches up to 6m span | 14 days |
Under sides of beam and arches up to 6m span and up to 9m span | 21 days |
Under sides of beam and arches over 9m span | 28 days |
0 comments:
Post a Comment